Milestone Dates -
Week 1 - Tues 23 & Thurs 25
- Concept and 'Fleshing out' Details
Week 2 - Tues 30 & Thurs 2 - July
- Female Model 'Fleshed Out'
Week 3 - Tues 7 & Thurs 9
- Female Fully Model/ Work on Clothes
Week 4 - Tues 14 & Thurs 16
Week 5 - Tues 21 & Thurs 23
- Female and Clothes Fully Textured
Week 6 - Tues 28 & Thurs 30
Week 7 - Tues 4 & Thurs 6 - August
- Continue Working on Male Model
Week 8 - Tues 11 & Thurs 13
- Male Fully Model and Textures
Week 9 - Tues 18 & Thurs 20
- Male Model
- Fix up anything that needs to be fix.... like textures, models
Week 10 - Tues 25 & Thurs 27
- Fix up anything that needs to be fix and finished.